Guidelines

To ensure satisfactory operation of these fuse holders throughout their service life, it is recommended that the following procedure be carried out at regular intervals (at least once a year) as part of a planned maintenance schedule. Where the environment or service duty is severe there may be a need for inspection at shorter intervals.

 

Procedure

  • Isolate the supply.
  • Withdraw the fuse carriers and inspect fuse tags and carrier contacts (SC100) for any signs of damage.
  • Check all cable terminal screws and fuse link fixing screws (SC100) to ensure that the correct torque has been applied.
  • Wipe clean and remove any oxidation from the fuse link blades or carrier contacts (SC100).
  • Apply a small amount of a proprietary electrical contact lubricating grease after ensuring that all contact areas are clean.
  • Re-fit the fuse carriers and re-connect the supply.

 

Important Note

The use to which these products are put and their service environment are outside our control. Therefore, particular care should be taken to follow these guidelines during installation or maintenance. No responsibility can be accepted by GE Power Controls Ltd if these guidelines are not followed.

 

(From Red Spot catalogue.)